Live-Grid Operation and Maintenance of the 35 kV/121 MVA Superconducting Cable System
Live-Grid Operation and Maintenance of the 35 kV/121 MVA Superconducting Cable System作者机构:The authors are with Department of development of lnnopowerSuperconductor Cable Co.Ltd (Innopower) Beijing 100176 China
出 版 物:《Journal of Electronic Science and Technology of China》 (中国电子科技(英文版))
年 卷 期:2008年第6卷第2期
页 面:108-111页
学科分类:080901[工学-物理电子学] 0809[工学-电子科学与技术(可授工学、理学学位)] 08[工学]
基 金:This work was supported in part by the Chinese Ministry of Science and Technology under Grant No. 2002AA306154, 2004AA306110,2005AA306120 and 2006AA03Z207 the Beijing Municipal Scienceand Technology Commission under Grant No. H020420010210 the Yunnan Provincial Science and Technology Department under Grant No.2003BABCA05A041 and 2003530101000415
主 题:Power grid power transmission,superconductivity superconducting cable.
摘 要:A 33.5 m, 35 kV/121 MVA, three-phase, warm dielectric HTS power cable system was successfully installed and activated in China Southern Power Grid at the Puji substation in Kunming on April 19th of 2004, supplying electricity to four industrial customers (including two metallurgical refineries) and a residential population of about 100000. In this paper, we give an update on the operation and maintenance status of the system and comments on reliability issues. We conclude that the superconducting cable system is currently quite robust and feasible for particular utility applications, and it will be improved by advancement in cryogenic equipment and system technology.